Week of January 26

A team of volunteer "SuperHeroes" descends to do the interior framing this week, including Fred & Wendy Jonasen, Jack LaBarre and friends, and Mike Ackerman.


Mike Ackerman is still smiles, even after having to come out an extra day due to a material delay.

Things start to take shape.

With the floor trusses and upper storage loft in place, our plumber gets back to work with rough in. Here, Paul installs lines for compressed air.

The Swanville Gang returns, this time to finish off interior steel.


Shown is our electrical contractor from BEAM Electric (Sauk Centre), getting a real charge out of his work.
Hydronic floor heat is hooked up, powered by an electric boiler. Shop heat will be on a "dual fuel" program offered by the local power company, and will be very cost effective to operate.